Skip to main content

What matters most to you in Delaware County? Take the survey →

active OH-DC-0012

Meta New Albany Data Center (original campus)

Campus: Meta New Albany

Owner
Meta
Operator
Meta
Primary use
hyperscale
Power
200 MW (est)
estimated IT load (5 buildings, pre-AI era)
Size
2,500,000 sq ft
Land area
345.00 acres
In service
January 2020 (actual)
Location
New Albany, Licking

Timeline

  1. announced 2017-08 (unknown)
  2. groundbreaking 2018-01 (unknown)
  3. buildings 1-2 2020 (unknown)
  4. building 3 2021 (unknown)
  5. buildings 4-5 2022 (unknown)
  6. investment >$1.5B (unknown)
  7. Green Chapel temp 2026-2028 (unknown)

Data confidence

Location
High
Owner Operator
High
Phase
High
Mw
Medium
Sqft
High
In Service
High
Buildings
High
Land Area
High
Primary Use
High

What we are still verifying

MW analogue-based. Socrates/PowerConneX BTM do NOT serve this campus.

Spot an error? Email a correction with the record ID OH-DC-0012.