active
OH-DC-0017
Google New Albany Data Center
Campus: Google New Albany
Owner
Google (Montauk Innovations LLC)
Operator
Google
Primary use
hyperscale
Power
250 MW
(est)
estimated current operational
Size
170,594 sq ft
Land area
Unknown
In service
Unknown
Location
New Albany, Licking
Timeline
- 2018 Montauk Innovations acquires initial parcel (unknown)
- 2019-Q4 $600M groundbreaking (unknown)
- 2020-03 AEP permanent service energized (unknown)
- 2022 $1B expansion (unknown)
- 2023-08 part of $1.7B Ohio trio (unknown)
- 2024-06 part of $2.3B Ohio commitment (unknown)
- 2025-06 +80 acres $63M (unknown)
- 2025-11 TotalEnergies 15-yr 1.5 TWh Montpelier solar PPA (unknown)
Sources
Local government
Other
- https://baxtel.com/data-center/google-new-albany-ohio
- https://www.aepohiowire.com/aep-to-power-googles-new-data-center/
- https://www.aepohio.com/lib/docs/ratesandtariffs/ohio/AEP-Ohio_DCT_Load_Study_Letter_25.11.7.pdf
- https://totalenergies.com/news/press-releases/united-states-totalenergies-supply-renewable-power-googles-data-centers-15
Industry reporting
Data confidence
Location
High
Owner Operator
High
Phase
High
Mw
Low
Sqft
High
In Service
High
Buildings
Medium
Land Area
Low
Primary Use
High
What we are still verifying
Single-building sqft (170,594) is one permit, not campus total; campus aggregate is 1M+ sqft across 6 operational buildings + 1 in build. No public per-site MW disclosure from Google or AEP Ohio.
Spot an error? Email a correction with the record ID OH-DC-0017.