phase 4
OH-DC-0022
AWS Sidney Data Center (Project Galaxy)
Campus: Project Galaxy
Owner
Amazon Data Services
Operator
Amazon Web Services
Primary use
hyperscale
Power
400 MW
(est)
contracted grid load (AES Ohio town hall)
Size
Unknown
Land area
243.00 acres
In service
December 2028
(expected)
Location
Sidney, Shelby
Timeline
- annexation petition 2025-07 (unknown)
- CRA approved 2025-10-27 (unknown)
- PILOT $50M/15yr (unknown)
- site clearing 2026-03-02 (unknown)
- town hall 400MW disclosed 2026-03-06 (unknown)
- operations target 2028-12-31 (unknown)
- jobs by 2030-12-31 (unknown)
Sources
Industry reporting
Other
Data confidence
Location
High
Owner Operator
High
Phase
High
Mw
Medium
Sqft
Low
In Service
Medium
Buildings
Low
Land Area
High
Primary Use
High
What we are still verifying
400 MW from town hall disclosure, not formal FERC filing. No EPA air permit for generators yet. Building count/sqft not disclosed. Utility: AES Ohio (not AEP). Township moratoriums under discussion nearby.
Spot an error? Email a correction with the record ID OH-DC-0022.