phase 3
OH-DC-0030
EdgeConneX Ashville Campus
Owner
EdgeConneX
Operator
EdgeConneX
Primary use
hyperscale
Power
800 MW
(est)
behind-the-meter generation capacity (OPSB filing)
Size
Unknown
Land area
680.00 acres
In service
June 2027
(expected)
Location
Ashville, Pickaway
Timeline
- proposal surfaces 2025-11 (unknown)
- 180-day moratorium enacted 2025-12-20 (unknown)
- annexation of 490ac denied 4-2 2026-02-02 (unknown)
- EdgeConneX offers $102M package 2026-02 (unknown)
- Resolution 06-2026 term summary approved 5-1 2026-04 (unknown)
- PowerConneX OPSB first public meeting 26-196-EL-BGN 2026-04-01 (unknown)
- full dev agreement deadline 2026-05-07 (unknown)
- OPSB application expected 2026-Q3 (unknown)
- OPSB decision anticipated 2026-10 (unknown)
- construction start target 2026-Q3 (unknown)
Sources
Industry reporting
Other
- https://www.circlevilleherald.com/community/plans-for-ashville-data-center-complex-revealed/article_4e01a5a8-8df5-4115-911d-cff2b10f86b0.html
- https://www.circlevilleherald.com/community/ashville-council-votes-5-1-to-adopt-the-edgeconnex-term-summary-resolution/article_6a335fd7-4406-411d-b8ea-178155601d5c.html
- https://www.thebrockovichreport.com/p/they-want-to-put-a-data-center-above
News
Data confidence
Location
High
Owner Operator
High
Phase
High
Mw
Medium
Sqft
Low
In Service
Medium
Buildings
Medium
Land Area
High
Primary Use
High
What we are still verifying
mw_value=800 is BTM gas generation capacity (OPSB filing), not IT load. Full-buildout 1.8 GW substation from leaked site plan, not OPSB-filed. End user/tenant not disclosed. Ohio EPA air permit for diesel backup not yet filed. Commercial Point legal challenge pending. Teays Valley Aquifer contamination risk flagged.
Spot an error? Email a correction with the record ID OH-DC-0030.