phase 3
OH-DC-0033
Google Lima Area Data Center (Project BOSC)
Campus: Project BOSC
Owner
Google (Bistrozzi LLC)
Operator
Google
Primary use
hyperscale
Power
316 MW
facility peak (115 generators × 2.75 MW from Ohio EPA permit)
Size
Unknown
Land area
200.00 acres
In service
Unknown
Location
American Township (near Lima), Allen
Timeline
- site proposed 2024-12 (unknown)
- land purchases complete 2025-08 (unknown)
- water ordinance 2025-09 (unknown)
- Ohio EPA draft air PTI hearing 2026-03-11 (unknown)
- comment closed 2026-03-18 (unknown)
- Google confirmed 2026-03-16 (unknown)
- AEP NE Lima-Columbus Grove 69kV rebuild 2026-2027 (unknown)
- construction expected 2026-2030 (unknown)
Sources
Industry reporting
Other
- https://www.limaohio.com/top-stories/2026/03/03/data-center-public-hearing-set-opponents-also-organizing/
- https://www.limaohio.com/top-stories/2026/03/16/google-officially-behind-data-center-project/
- https://baxtel.com/data-center/north-cole-st-data-center
- https://www.aeptransmission.com/ohio/NELima-ColumbusGrove/
Data confidence
Location
High
Owner Operator
High
Phase
High
Mw
High
Sqft
Low
In Service
Medium
Buildings
Medium
Land Area
High
Primary Use
High
What we are still verifying
Generator manufacturer redacted (likely Cummins QSK78). Unclear if 115 generators serve all 3 buildings or Phase 1 only. Building sqft not disclosed. Full-buildout with all 3 buildings could reach 500-600 MW.
Spot an error? Email a correction with the record ID OH-DC-0033.