phase 4 OH-DC-0049

Meta Bowling Green Data Center

Owner
Meta Platforms (Liames LLC)
Operator
Meta
Primary use
hyperscale
Power
180 MW
peak IT demand (Meta-stated)
Size
715,000 sq ft
Land area
280.00 acres
In service
July 2027 (expected)
Location
Bowling Green, Wood

Timeline

  1. Campus construction starts (Liames LLC) 2023-fall (unknown)
  2. Meta publicly announced 2025-04 (unknown)
  3. Apollo OPSB filing 25-0973-EL-BGN 2025-11-05 (unknown)
  4. OPSB approves Apollo 2026-02-03 (unknown)
  5. Apollo construction starts 2026-02-09 (unknown)
  6. Apollo partial ops + DC partial energization 2027-mid (unknown)
  7. Apollo full ops + DC full capacity 2027-late (unknown)

Data confidence

Location
High
Owner Operator
High
Phase
High
Mw
High
Sqft
High
In Service
High
Buildings
High
Land Area
High
Primary Use
High