phase 4
OH-DC-0057
Microsoft Heath Campus
Owner
Microsoft
Operator
Microsoft
Primary use
hyperscale
Power
250 MW
(est)
estimated IT load (5 buildings)
Size
245,000 sq ft
Land area
227.00 acres
In service
January 2028
(expected)
Location
Heath, Licking
Timeline
- announced 2024-10 (unknown)
- paused 2025-04 (unknown)
- resumed 2025-11 (unknown)
- groundbreaking 2026-02 (unknown)
- grading complete target 2026-11 (unknown)
- first building target 2028 (unknown)
Sources
Industry reporting
Other
Data confidence
Location
High
Owner Operator
High
Phase
High
Mw
Low
Sqft
Low
In Service
Medium
Buildings
Medium
Land Area
High
Primary Use
High
What we are still verifying
MW analogue-based. Per-building sqft estimated from New Albany precedent (245k). No FERC/OPSB filing. No longer paused.
Spot an error? Email a correction with the record ID OH-DC-0057.